This project involves the hidden danger rectification of the air conditioning system for Building 2 of Suzhou Jinji Lake Data Center. It is equipped with one YC16VC diesel generator set with a rated power of 2200kW. The unit serves as the emergency standby power supply for the building's air conditioning system and other critical loads, aiming to enhance the stability and reliability of the on-site power supply system.
The 2200kW (16VC) diesel generator set has passed comprehensive factory inspection and performance testing. It completed on-site acceptance and was officially delivered in June 2022, with all supporting technical documents, operation manuals and spare parts fully supplied.

The unit and its auxiliary systems are designed with expandability. The civil foundation, cable trenches, fuel pipelines and control systems are all reserved with expansion interfaces, supporting subsequent unit parallel operation and system capacity expansion to accommodate the long-term load growth of the data center.
This rectification renovation effectively eliminates the single-point power supply hazards existing in the original air conditioning system. The commissioning of the 2200kW unit ensures sustained cooling capacity during mains power outages, which provides a solid guarantee for the safe and stable operation of the data center building.