Delivery of 16 Units of 1800kW Generators (16VC) for Phase I of Dongguan Tuanbowah H Data Center

Leave a message

Phase I of the Dongguan Tuanbowah H Project Data Center is equipped with 16 units of 1800kW generators (model 16VC) as its core standby power supply. All generators were delivered on-site, installed, and no-load commissioned in April 2023, then handed over to the O&M team for regular standby, ensuring uninterrupted power for critical equipment like server clusters and UPS systems during mains outages.
 
All delivered 1800kW (16VC) generators passed factory and on-site inspections, meeting relevant technical requirements and design specifications. With a 16-cylinder V-type arrangement, they have a start-up response time of ≤ 15 seconds, support smooth 50%-100% load switching, and feature intelligent monitoring for remote control and fault alerts, reducing O&M workload.
 
info-1331-554
 
In April 2023, a joint acceptance team (construction, supervision, and generator supplier) completed item-by-item inspections and document verification. All 16 generators met delivery standards and were handed over, marking full deployment of the Phase I standby power system and supporting subsequent cabinet commissioning.
 
The delivery enhanced the data center's power redundancy to handle sudden mains outages and grid fluctuations. The O&M team will conduct regular maintenance (inspections, oil replacement, load testing) to ensure optimal generator performance and long-term stable operation of the data center.