Aug 28, 2026

1×1000KW Gas Generator Set (Yuchai 12VCN) for Coal Mine Gas Power Project in Jiaozuo, Henan

Leave a message

One set of Yuchai 12VCN 1000kW gas-fired generator set is officially applied to the coal mine gas power station of Jiaozuo Coal Industry, Henan Province. Powered by onsite drained coal mine methane, the unit provides stable and continuous power supply for mine production equipment, underground ventilation, gas drainage systems and daily auxiliary facilities, realizing efficient recycling utilization of mine waste gas resources.

 

info-637-520

 

1. Background: Jiaozuo Coal Mine Gas Utilization Project

Jiaozuo is an important traditional coal industrial base in Henan with complete coal mining and gas extraction infrastructure. Large amounts of coal mine methane are continuously drained during mining operations. Direct emptying of methane causes serious environmental pollution, greenhouse gas emissions and potential safety hazards. This gas-to-power project effectively converts waste coal mine gas into clean electric power. The generated electricity supports core mine production loads, while surplus power can be connected to the local public grid. The local mining environment features unstable methane concentration, humid air and fine mine dust, which put forward strict requirements on gas adaptability, anti-corrosion performance and long-term continuous operation of gas generator units.

 

2. Why Adopt 1000KW Yuchai 12VCN Gas-Fired Unit

The Yuchai 12VCN 1000kW gas generator serves as the core power equipment for this Jiaozuo mine gas power station. Equipped with a 12-cylinder V-type gas engine, the unit is professionally optimized for variable coal mine methane quality. It adapts well to frequent fluctuations of methane concentration and maintains stable combustion and consistent power output under complex working conditions. The whole machine adopts upgraded anti-dust and anti-corrosion treatments for air intake systems, pipelines and control components, effectively resisting mine dust and humid corrosion. The integrated skid-mounted structure features compact layout, convenient on-site installation, simple commissioning and low daily maintenance cost, perfectly matching long-term stable operation demands of mine power stations.

 

3. Key Technical Specifications

Engine: Yuchai 12VCN, 12-cylinder V-type gas engine (×1)

Rated Power: 1000 kW

Configuration: skid-mounted, grid-parallel capable

Fuel: extracted coal mine methane / coal mine gas

Rated Speed: 1000 r/min

Rated Frequency: 50 Hz

Control: intelligent gas adaptive control system, full multi-parameter safety interlock protection

Note: customized anti-dust and anti-corrosion design for humid and dusty coal mine working conditions

 

4. Operational Value Since Commissioning

After official commissioning, the Yuchai 12VCN 1000kW gas generator set fully realizes harmless disposal and resource utilization of coal mine methane. It greatly reduces methane emission pollution, lowers the mine's dependence on municipal grid power, and cuts enterprise power consumption costs. With excellent environmental adaptability and reliable continuous operation performance, the unit reduces equipment failure frequency and extends service life of core parts, bringing stable economic, environmental and safety benefits for the Jiaozuo coal mine power project.

 

5. Frequently Asked Questions (FAQ)

Q: What kind of gas does the Yuchai 12VCN unit use for power generation?

A: It runs on onsite drained coal mine methane. The intelligent adaptive system automatically adjusts combustion parameters to adapt to unstable methane concentration in actual mine conditions.

 

Q: Is this unit suitable for humid and dusty coal mine environments?

A: Yes. The unit adopts professional anti-dust filtering, sealing and anti-corrosion coating technologies, which can steadily adapt to humid, dusty and complex underground mining working conditions.

 

Q: Does this generator support grid connection operation?

A: Yes. It supports grid parallel operation, enabling surplus power to be fed into the local public grid to maximize energy utilization efficiency.

 

Q: Can the power station be expanded in the future?

A: Yes. More 1000kW same-type units can be added and operated in parallel to expand the total installed capacity and meet increasing power demand of mine production.

Send Inquiry